7.9.09

U2 Stage Sets Trendsetting Hydraulics

The stage for U2’s 360° Tour is being constructed using Enerpac’s Synchronous Lift System, giving spectators all around the stage an unobstructed view of the band.

The Belgian company Stageco has constructed three gigantic, identical stages for the current U2 360° Tour. What makes this project special, is that high-pressure hydraulics are being used for the first time ever to assemble and dismantle the 254 ton construction - also known as “the claw”. Together with Enerpac, Stageco has developed a unique system, based on Enerpac’s Synchronous Lift System, to raise the modular construction to a height of 33 yards quickly and safely.

Being able to put on bigger and better shows than your competitors gives you a trump card in the entertainment world. Performances and tours by famous artists and bands have to look good, as is demonstrated by the glitz and special effects that are usually the main feature. The stage is crucial, and this is no different in U2’s 360° Tour. For this world tour, set designer Willy Williams and stage architect Mark Fisher came up with “the claw”, a 33 yards high stage construction on four legs, giving spectators all around the stage an unobstructed view of the band.



(“The claw”, a 33 yards high stage construction on four legs, giving spectators all around the stage an unobstructed view of the band.)



Stageco, a specialist company based in Tildonk, Belgium, was contacted for the construction of the stage. This was not the first time – Stageco also designed and built the stages for one of U2’s previous tours, the PopMart Tour in 1997.

Stageco is an undisputed market leader and primarily sets itself apart through customization. Over the years, the company has built stages for tours by artists such as the Rolling Stones, Bon Jovi, Tina Turner, Elton John and Johnny Hallyday. Stageco provides a complete package, from technical design and manufacture, right up to logistics.

Since there is only a relatively short time between performances and a total of 7 to 8 days are needed to assemble and dismantle the stage construction, three whole stages have been constructed, which are used following the “leapfrogging” principle: one is used for the show, whilst the second is already being built at the next location and the third is being dismantled at the previous location.

Speed

One of the construction requirements was that the stage could be built and taken down again in a relatively short time. The challenge for Stageco was therefore how to assemble and dismantle the massive 254 ton construction each time. Logistics naturally also needed to be considered and a solution had to be found for the installation of the techniques (light and sound) and the special 66 ton video screen that also had to be raised and lowered each time. Chain hoists and winches are normally used for stages, with the support of relatively light mobile cranes where required. However, the load in this project was so great that a different solution was called for. One of the alternatives considered was the use of extremely heavy mobile cranes with a lifting capacity of at least 440 to 550 tons.

However, there was doubt as to whether such cranes would fit inside the stadiums where the concerts were due to take place and whether they could be stabilized sufficiently. The use of such cranes is also very expensive. Another alternative was a temporary hoisting construction and the use of hydraulics, for example, hydraulic strand jacks. Stageco eventually joined up with Enerpac as a source of new ideas and a customization-oriented partner.

The requirement was that the system had to be more or less plug and play. A ready-to-use hydraulic unit was required that would only need to be connected to the electricity supply and the operating computer. Together, the two companies came up with a highly effective solution which incorporated Enerpacs custom designed Synchronous Lift System to use high-pressure hydraulics for the first time ever for such heavy loads.



Gradual Lifting

The steel stage construction consists of a central “block” which rests upon four legs, each made up of six sections. The central block is gradually lifted off the ground in 38 steps and a section is added to each of the four legs after every 6 or 7 steps.

A temporary truss (lifting portal) containing a supporting frame at the top has been made for each leg.

Within each truss, a hydraulic pump unit, four high-pressure lifting cylinders (5000 psi), each with an applied pulling force of 22 tons and a 24 inch stroke, and four 0.6 ton low-pressure (870 psi) locking cylinders, each with a stroke of 10 inch, are all attached to a supporting frame, which moves along the guide rails.

The complete hoisting system for each stage therefore consists of 16 lifting cylinders, 16 locking cylinders and 4 fully hydraulic units. The lifting cylinders are fitted with a pressure transducer, a built-in stroke sensor and two proximity switches. The locking cylinders are also fitted with two proximity switches.

The hydraulic pump unit includes individual pumps - one for the lifting cylinders and one for the locking cylinders. The pump units are controlled according to the master/slave principle from a central operating computer on the ground, which has a touch screen with images showing the position of the various hydraulic cylinders and their position within the lifting portals. The force of each lifting cylinder and each lifting portal is also displayed, along with the total force. What is more, a local PLC has been installed on each platform so that the lifting platform can be operated locally if necessary.



Up & Down

First of all, the complete pump units are positioned in the lifting portals using a small mobile crane. At the beginning of the lifting process, the ends of the central block rest on the supporting frames with the Enerpac units.

When the frame is lifted, the top beams are first raised one step hydraulically, and then locked mechanically using locking pins and the hydraulic locking cylinders. The bottom locking pins are then cleared hydraulically and the cylinders raise the load to the same height. In this way, the four hydraulic units lift themselves in the lifting portals with the load, as it were, at a net speed of around 11 yards per hour.

Lift synchronism is vital here due to the torsion stress that occurs. Stageco works with a tolerance of 0.2 to 0.4 inch. This may seem like a lot, but it is adequate since the lifting portals are 38 inches apart. The operating computer’s display also shows that the load in the four portals remains in perfect balance. The display shows which steps in the lifting process have already been completed. The operator does, however, need to give the system a command for each step.

After the claw has been assembled, the pump units are lifted out of the lifting portals with a crane, and the lifting portals are then removed. The system works according to the same principle but, of course, in the opposite direction when the whole construction is later lowered and dismantled. The pump units are then back on the ground and can be stored ready for transport to the next location.



Safety Trump Card

Stageco has made no concessions whatsoever as far as safety is concerned. The mechanical locking of the lifting platforms, for example, was an extremely important element. Enerpacs computer-controlled Synchronous Lift System also fulfilled this requirement perfectly.

Every step in the lifting process is controlled, and the next step can only be performed when all the required conditions have been fulfilled. The system also gives information on the position the load is in and how the tension is distributed during lifting. The Enerpac system measures the forces continuously and in real time.

Although the operational speed is significant, Stageco considers safety to be one of the greatest advantages of this technology. Since the three stages will be travelling across the whole world over the next two years, the emphasis is also on reliability and durability. According to Stageco, another advantage is that Enerpac has an international presence and operates worldwide.

It is clear that shows will continue to get bigger and better in the entertainment world. Since Stageco now has this new technology in house, set designers will also have much more freedom and it will be possible to build spectacular stages at many more locations. In short, this is a technological step that is setting a new trend.

Stageco, based in Tildonk, Belgium, was established 25 years ago and has branches in France, the USA, the Netherlands, Germany and Austria. However, the company operates throughout the whole world. Stageco is not the only stage construction company out there, but it is the market leader and it primarily sets itself apart through customization.

The company has an extensive stock of standard modular stages that can be rented out. Stageco is a company that deals with the entertainment world in an extremely innovative manner. The company is constantly on the lookout for solutions to certain problems that occur in the industry, and modernizes and applies these solutions within its own field.

For more information visit www.stageco.com

source: pddnet

No comments: